Propst Construction Co. v. North Carolina Department of Transportation

Filed: April 20, 1982.

PROPST CONSTRUCTION CO.
v.
NORTH CAROLINA DEPARTMENT OF TRANSPORTATION



Appeal by plaintiff from Wood, Judge. Judgment entered 21 April 1981, in Superior Court, Montgomery County. Heard in the Court of Appeals 9 February 1982.

Becton, Judge. Judge Hedrick and Judge Hill concur.

Becton

Plaintiff's Appeal

Plaintiff assigns as error the trial court's granting of summary judgment in favor of defendant and its denial of partial summary

judgment in favor of plaintiff. Four arguments are presented. For the reasons that follow, we believe the trial court erred in not submitting the case to the jury.

First, plaintiff contends that the doctrine of prevention relied upon by defendant in its motion for summary judgment was inappropriate under the facts of this case. The doctrine of prevention is that "one who prevents the performance of a condition, or makes it impossible by his own act, will not be permitted to make advantage of the nonperformance." Harwood v. Shoe, 141 N.C. 161, 163, 53 S.E. 616, 616 (1906). In order to excuse nonperformance, the conduct on the part of the party who allegedly prevented performance "'must be wrongful, and . . . in excess of his legal rights.'" Goldston Brothers v. Newkirk, 233 N.C. 428, 432, 64 S.E.2d 424, 427 (1951), quoting Page on Contracts, Vol. 5, Sec. 2919, p. 5145. See also 6 Corbin on Contracts ยง 1264 (1962).

Defendant's contention, set forth in its motion for summary judgment, was that plaintiff, by failing to provide accurate weight scales, prevented defendant's performance of the contract and should, therefore, be estopped from taking advantage of its failure. From the documents considered on the motion for summary judgment, however, it appears that defendant's contention oversimplifies a more complex factual situation. When we view the evidence set forth in those documents in the light most favorable to the plaintiff, as must be done in ruling on a motion for summary judgment, Zimmerman v. Hogg & Allen, 286 N.C. 24, 29, 209 S.E.2d 795, 798 (1974), we find that it tended to show that plaintiff, in accordance with the contract, provided the scales for weighing the stones for the highway project; that, under the terms of the contract, defendant had the responsibility to check the scales prior to use; that there was a representative of defendant present at the scales, signing each weight ticket; that, at about the midpoint of the project, the superintendent of hauling (who worked for Dickerson, Inc.) informed defendant's representatives that something was wrong with the scales, "because the weight had . . . [fallen] off so much;" and that the DOT representative agreed that something appeared to be wrong.

When deposed, an employee of Piedmont Scale Service stated that he examined the scales on 22 August 1978, after the project was completed, and found them broken. The scales were "underweighing"

the vehicles, and the heavier the true weight of the vehicle, the greater the degree of error. Although the contract between plaintiff and defendant did not establish which party had the continuing responsibility to check the scales, Dickerson's superintendent of hauling stated in his deposition that the State "has a man that comes around and checks the scales." Nowhere in defendant's motion and nowhere in the documents considered on the motion for summary judgment do we find any allegation or evidence that plaintiff caused the scales to malfunction.

After reviewing the foregoing evidence, this Court agrees with the plaintiff that the doctrine of prevention does not apply to the circumstances of this case. Again, it is not clear who, plaintiff or defendant, had the responsibility to check the accuracy of the scales. Based upon the deposition of Dickerson's superintendent of hauling, it appears that the defendant normally checked the accuracy of the scales. Under the evidence considered on defendant's motion for summary judgment, plaintiff cannot be said to have "prevented" defendant's performance under the contract, i.e., defendant's payment for the total amount of ABC delivered to the project.

Under the contract, defendant was obligated to pay for the actual tonnage of ABC delivered for the Highway 220 project. Defendant, however, paid only for the amount of ABC which showed on the allegedly defective scales. We believe that the evidence set forth at the hearing on the motions for summary judgment established a genuine issue of material fact as to how much ABC was actually delivered to the project. During the project, as the ABC was delivered to the stockpiles, plaintiff's employees had maintained records of tonnage used on the project by calculating an average weight per truck per day and multiplying that average by the number of trucks on the given day. The total figure they obtained was 177,334.25 tons. Compared with this is the estimate of 170,974 tons made by defendant in "cross-sectioning" the stockpiles. The stockpiles were under the control and supervision of defendant and were depleted at the end of the project. This evidence as well as the ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.